Leeds Update

The next 2-3 weeks will see the final commissioning work at our new state of the art datacentre in Leeds. The exterior of the building and the compound are now complete.

We will complete the battery and UPS installation this week and commission the airconditioning shortly after that. We will be kitting out our new NOC and reception area next week.

The building will be cleaned by a team of specialist data centre cleaners to recognised ISO clean-room standards and the initial batch of comms equipment will be installed and configured ready for the first customers to move in

Here are some pictures of the cold aisle pods we have installed in the rooms. We have 2 rooms completed, but we have only installed the pods in one room for now, the other will follow shortly.