Construction is now underway on Hall 4 of our Wakefield Data Centre, which will give us the capacity for another 150 racks spread over 350m2 of technical space.

Right now, we are installing the Aircon and power systems and linking everything together; that's the last big bit of plant to be delivered, so it's all connection and commissioning work for the next 6 weeks.

The installation includes:

  • 2x Airedale 420KW Free Cooling Chillers
  • 4x CRAC Units (will expand to 8 later)
  • 2x UPS Panel Boards
  • 2x Eaton UPS (will expand to 4 later)
  • Extension of Existing Gas Suppression System
  • Raised Access Floor
  • Busbar Power Distribution System
  • LED Lighting
  • Airedale BMS System

2 x Airedale 420KW freecooling chillers

[gallery columns="2" size="large" link="file" ids="24915,24914"]

Panel Boards and UPS

[gallery columns="2" size="large" link="file" ids="24912,24913"]

As you can see, we're busy improving our infrastructure. The expansion of Data Hall 4 is the next step in enabling us to better serve our customers.

Stay tuned for more updates...

Rik Williams

Head of DC Operations


For more information on our Data Centres, download our Data Centres Brochure.

Related stories...

Latest blog releases of interest...

Ensuring Data Centre Availability…

There are many data centre providers across the UK but how do...

Read more

The 'Art' of Cybercrime

In the wake of Da Vinci’s 'Salvator Mundi' recent record-breaking...

Read more

The Ease of Hacking in 2017

The Ease of Hacking in 2017 Hacking is everywhere. It’s all you hear...

Read more

Nottingham Office

Taking a look at the latest development in our newest office. Located...

Read more