DC3 Site Update

We thought we would give you a quick update on the progress of DC3.

The site is on track to open at the end of April and things are now moving on very quickly. 2 out of the 4 generators were delivered last week along with the fuel tanks. Now they are all in position the contractors are working on the cabling ready for the arrival of the mains distribution pannels which are due to be installed  W/C 23rd March. As you can see below the panels are currently being built and will be going through acceptance testing next week.

The brick built substation is also nearly complete ready for the installation of the dual HV switches next week.